Construction to Begin at Highway 6 and Wellington Road 22 Near Fergus

Project includes new multi-lane roundabout and replacement of the Cox Creek culvert

[Fergus, ON] – The Ontario government is moving forward with significant improvements at the intersection of Highway 6 and Wellington Road 22/8th Line, with construction to begin shortly on a project that will enhance safety, modernize infrastructure, and improve the long-term reliability of this important transportation corridor between Fergus and Guelph.

“I heard loud and clear from residents about the importance of moving forward with a roundabout at Hwy 6 and Wellington Road 22,” said Joseph Racinsky, MPP for Wellington-Halton Hills. “Thank you Minister Sarkaria for your dedication to ensure we got shovels in the ground as soon as possible.”

The project includes the installation of a new multi-lane roundabout, road improvements on Highway 6 and Wellington Road 22/8th Line and replacement of the Cox Creek culvert on Highway 6 north of the intersection. Additional work includes new lighting, drainage upgrades, roadside safety enhancements, signage improvements and pavement rehabilitation.

The Ministry of Transportation (MTO) has awarded the Highway 6 and Wellington Road construction contract to Capital Paving Inc. Once complete, the project will create a safer intersection for residents, commuters, commercial vehicles and visitors travelling through the area.

Construction impacts:

  • Advance construction and detour signage is scheduled for installation the week of June 29.
  • Initial closures are anticipated to begin the week of July 6, including a portion of Wellington Road 22 from east of the Cox Creek Winery entrance to west of the entrance at 7694 Wellington Road 22. During this time, Cox Creek Winery will remain accessible via Highway 6 only. A partial closure on Highway 6 is also expected on the west side of the roadway (outer southbound lane) north of the intersection.
  • Beginning the week of July 20, access from Highway 6 to both Wellington Road 22 and 8th Line will be closed. During this period, access to Cox Creek Winery will be maintained from the east. These restrictions are expected to remain in place until July 2027.
  • During the closure, local traffic east of Highway 6 will be detoured via Wellington Road 22, Jones Baseline, and Townline Guelph-Nichol, while traffic west of Highway 6 will be detoured via 8th Line, Wellington Road 7, and Wellington Road 51.
  • All work and timing is weather dependent. Travellers are encouraged to visit 511on.ca or follow @511Ontario for updates on road work and traffic impacts.